If you want to throttle tasks in a dag, you need to define its "concurrency" parameter.
"concurrency" defines how many running task instances a DAG is allowed
to have, beyond which point things get queued.
If you want to throttle tasks globally, look into this lines of the config file
The amount of parallelism as a setting to the executor. This defines
the max number of task instances that should run simultaneously
on this airflow installation
parallelism = 32
And
The number of task instances allowed to run concurrently by the scheduler
dag_concurrency = 16
The first is global, the second is the concurrency default value for all dags

Related

How should I pull from Pub/Sub using Compute Engine MIGs

In my personal case, Pub/Sub's pushes to a Python service on Cloud Functions are being unfeasible due to it's short timeout. So the idea of having a container-based managed instance group of Compute Engine instances sounds good, these instances can scale up/down based on Pub/Sub pending task count metrics. These machines' containers would run Python code on startup, the given code would PULL Pub/Sub and process the pulled job accordingly.
Contextualization aside, the question is: Is it a good idea? Are there any gotchas? As there would be several machines at scale, how could I guarantee that a same given 'queued task' would not be picked and have it's processing started on more than one of these machines? I know about ACKs, but ACKs should just be emitted when the task ends successfully, isn't it? What strategy to use to prevent the initially mentioned and other problems?

Django + Celery with long-term scheduled tasks

I'm developing a Django app which relies heavily on Celery task scheduling, using Redis as backend. Tasks can be set to run at a large periods of time, as well as in a few seconds/minutes.
I've read about Redis visibility timeout and consequences of scheduling tasks with timedelta greater than visibility timeout (I'm also in the process of dealing with it in a previous project), so I'm interested if there's anything neater than my solution, which is to have another "helper" task run 5 minutes before the "main" one needs to be executed, scheduling the "main" task to run in required time, storing task id in DB, and then checking in "main" task if the stored task id is the one that is being run. The last part (with task id storing) is required as multiple runs of "helper" task could spawn a lot of "main" task instances, but with this approach each will have different task id.
I really hate how that approach sounds and how it works, as if the task is scheduled to be run a month from current time, "helper" and "main" tasks are executed up to a hundred times.
I also know that it's an open issue, so I'm interested in more a neat workaround than a solution itself.
Having tested available options, in my opinion only using RabbitMQ as broker solves the whole problem.
Although it's a viable option for me, lack of some of redis configuration parameters (e.g. pool size) makes it unusable for those who are using hosting services with some limit on opened broker connection.

How is it that a mapreduce pipeline can run longer than 10 minutes?

MapReduce tasks are run within a parent pipeline, and of course we all know they can run for a very long time. But at the same time, the pipeline api documents that a pipeline must complete within 10 minutes (https://github.com/GoogleCloudPlatform/appengine-pipelines/wiki/Python). What is the proper way to understand this?
Thanks.
That pipeline documentation is really old... when it was written, tasks were limited to 10-mins. Now you can configure a non-default modules (used to be called a "backend") using basic/manual scaling that will allow a task to run for 24hrs
https://cloud.google.com/appengine/docs/python/modules/#Python_Instance_scaling_and_class
(NOTE: if you run a task on an auto-scaled module, it will still be limited to 10-mins)
The entire pipeline doesn't have to be limited to 24hrs though. The "root" pipeline (the first task that runs) can yield many child pipelines, and those each can further yield other pipelines... each pipeline is a task that has to run within the allotted time (10mins or 24hrs)... when it is done, it signals the parent to wake-up and finish... so the overall pipeline could run for days or months or whatever
We have our app split into two modules, one for the front-end (default, auto-scaled) that handles web requests, and one for the "back end" (basic scaling) that runs all of our tasks

Concurrency in running Oozie workflow: how many and how to throttle

Let us say we have a Oozie workflow that has a copy action node then a Shell action node. Can I start multiple instances of such a OOzie workflow and run them in parallel? How about the concurrency number could spike to thousands and/or even millions level. Is that possible, or even Oozie supports that high level concurrency?
If not, then we will have to consider throttling and enforce a cap on how many concurrent Oozie workflow instances can be. We'd prefer to throttle this on server/Oozie side (basically with any out of box Oozie software functionality), not on client/callee side. For example, we have a huge launch script with lines like this. We want to run that in a single shot, then let Oozie figure out how to throttle all these instances on itself. We don't want to split it into multiple smaller chunks, then kick off one chunk at a time.
oozie job -oozie http://myhost.com:11000/oozie -config job1.properties -run
oozie job -oozie http://myhost.com:11000/oozie -config job2.properties -run
......
oozie job -oozie http://myhost.com:11000/oozie -config job1000000.properties -run
You will not be able to have a higher Oozie workflow concurrency than the number of map slots on your cluster because a Shell action is run by a one-mapper-zero-reducer MR job.
If you have many instances of a workflow to get through then the best mechanism is to use an Oozie coordinator. This will keep track of the completion of each instance and easily manage concurrency. An Oozie coordinator has a <concurrency> tag that controls how many instances of the workflow will execute in parallel, and a <throttle> tag that controls how many instances are brought into a waiting state before there is free concurrency for one to begin.
See: https://oozie.apache.org/docs/3.1.3-incubating/CoordinatorFunctionalSpec.html#a6.3._Synchronous_Coordinator_Application_Definition
Note that the default behavior of an Oozie coordinator is to wait 5 minutes between each polling of whether a new instance should be created. If your workflows run in less than 5 minutes then the process will bottleneck on this interval. You can change this with the oozie.service.CoordMaterializeTriggerService.lookup.interval property (in seconds) in your oozie-site.xml file.

Celery all generated tasks status

Django produces multiple Celery tasks through chains in one script run (f.e. if / is opened in browser, 1000 tasks are called by delay method).
I need something that will restrict new task generation, if tasks, queued in previous script run, are still running.
You need a distributed lock for this, which celery doesn't offer natively.
For these kinds of locks I've found redis.Lock useful to most cases. If you need a semaphore, you can use redis' atomic incr/decr functions along with some kind of watchdog mechanism to ensure your processes are still running.
You can restrict the number of tasks of one type running at the same time by setting:
rate_limit = “1000/m”
=> only 1000 tasks of this type can run per minute.
(see http://docs.celeryproject.org/en/latest/userguide/tasks.html#list-of-options)